2018下半年信息系統(tǒng)監(jiān)理師上午真題(八)

信息系統(tǒng)監(jiān)理師 責(zé)任編輯:胡媛 2018-11-15

添加老師微信

備考咨詢

加我微信

摘要:希賽網(wǎng)軟考頻道小編為大家整理了2018下半年信息系統(tǒng)監(jiān)理師考試上午真題第八部分,供大家參考。

● __(71)__ techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .

(71)A. Schedule forecasts

B. Schedule compression

C. Change requests

D. Data analysis

● Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by __(72)__.

(72)A. negotiation

B. the court

C. lawyer

D. arbitration

● The organization shall undertake change in a planned and systematic manner, taking account of the review of the potential consequences of changes and taking action as necessary, to ensure the integrity of goods and services are maintained. This is called (  ).

(73)A. control of changes

B. control of plans

C. control of accounts

D. control of service

● Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved (  ).

(74)A. schedule baseline

B. cost baseline

C. cost output

D. cost input

● The top management of a company will review the organization’s management system, the management review will include consideration of :

( a ) customer feedback on quality

( b ) processes performance and product conformity

The purpose of management review is (  ).

(75)A. control of customers

B. control of measurements

C. control of qualities

D. control of opportunities

 

相關(guān)推薦:2018下半年信息系統(tǒng)監(jiān)理師真題匯總

點(diǎn)擊注冊(cè)會(huì)員>>>即可獲取信息系統(tǒng)監(jiān)理師免費(fèi)在線真題、觀看免費(fèi)公開課!

更多資料
更多課程
更多真題
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,本網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)考生以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

軟考備考資料免費(fèi)領(lǐng)取

去領(lǐng)取

!
咨詢?cè)诰€老師!