71、Blocks are storage units one by oneand fach block is linkealby()in Blockchain.
A、Hash
B、DES
C、RSA
D、DSA
72、The organization shall undertake root causeanalysis and determine potential actions to preventthe occurrence or recurrence of().
A、changes
B、services
C、problems
D、incidents
73、The highest level of quality management is ().
A、detect and correct the defects before the desirables are sent頭the customer as of the quality control process
B、use quality assurance to examine and correct the process it self and not just special defects
C、Incorporate quality into the ptanning and designing of the project and product
D、createa throughout the organization that is committed to quality in process and products
74、()helps to determine which individual project risks or other sources of uncertainty have the most potential impact onproject outcomes.
A、checklist analysis
B、sensitively analysis
C、decision tree analysis
D、simulation
75、In china,the security protection level of information system vs olivided into()levels.
A、3
B、4
C、5
D、6