2019下半年系統(tǒng)集成項目管理工程師上午真題(八)

系統(tǒng)集成項目管理工程師 責(zé)任編輯:胡媛 2019-11-11

添加老師微信

備考咨詢

加我微信

摘要:希賽網(wǎng)軟考頻道小編為大家整理了2019下半年系統(tǒng)集成項目管理工程師上午真題,以下為系統(tǒng)集成項目管理工程師基礎(chǔ)知識真題第八部分:

71、(  )contributes to monitoring and data collection by defining security monitoring and date collection requirements.

A、information continuity management

B、information catalogue management

C、information security management

D、information distribution management

72、(  )seek to perform root cause investigation as to what is Ieading identified trends.

A、incident management

B、problem management

C、change management

D、knowledge management

73、the (  ) is a graph that shows the relationship between two variables.

A、histograms

B、flowcharts

C、matrix diagrams

D、Scatter diagrams

74、(  )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.

A、identify risks

B、monitor risks

C、impIement risks responses

D、plan risk management

75、work performance information is circulated through(  ) processes.

A、 planning

B、 change

C、 improvement

D、 communication

更多資料
更多課程
更多真題
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,本網(wǎng)站提供的以上信息僅供參考,如有異議,請考生以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

軟考備考資料免費(fèi)領(lǐng)取

去領(lǐng)取

!
咨詢在線老師!